HELLENIC PETROLEUM – ASPROPYRGOS INDUSTRIAL COMPLEX
The most important projects that ALFA PI S.A. has executed in the Aspropyrgos Industrial Complex are:

   
CONSTRUCTION PERIOD
VALUE OF WORKS (€)
Sundry Mechanical Works, B' Semester 1991
June 91 - Febr. 92
145.144
Sundry Mechanical Works, A' Semester 1992
Febr. 92 - July 92
143.152
Sundry Mechanical Works for modifications & improvements
July 92 - July 93
183.727
Sundry Mechanical Works, B' Semester 1993
June 93 - March 94
173.833
Sundry Mechanical Works & Steel Construction
Feb. 94 - Dec. 94
247.590
Reconstruction & improvements of fire fighting installations of tanks Ρ8738, Ρ8702Α, Ρ8701I, Ρ8701D
April 95 - Sept. 95
112.551
Sundry Mechanical Works, A' Semester 1995
May 95 - Dec. 95
187.200
Reconstruction of 95 lines for the Shut-Down
April 95 - Aug. 95
75.401
Additional pipeline Φ6" & Φ8" for U-3400, as subcontractor of TECHNIPETROL
March 96 - June 96
181.952
Interconnection of Flare Gas Recovery Unit Z-5411
March 97 - Oct. 97
372.707
TIP Extension of U-4600: Equipment erection & pipeworks, as subcontractor of ZEUS (J&P)
Feb. 98 - Dec. 98
1.320.616
Improvement of steamtraps and steam systems in all units
Dec. 98 - Dec. 99
352.164
Maintenance work of heat exchangers of all units
Shut Down Sept. 99
1.040.117
Maintenance Works in Furnaces L-2101 A/B & L-3702 A/B
Shut Down Sept. 99
119.760
Change of Kero Tankage
June 01 - Μay 02
821.717
Supply of skilled labour for maintenance works (Annual contract)
Dec. 03 - Dec. 04
3.439.000
Erections works for Diesel Unit U-3400 Revamping: Civil Equipment Erection & Pipework
Febr. 04 - Dec. 04
2.453.000
Maintenance works for Unit U-3400
Shut Down - 2004
252.500
Supply of labour for cleaning & transportation works (Annual contract, extended to 2005)
Jan. 04 - Dec. 05
580.000
Maintenance Works in Furnaces L-3301/2/3/4/1N/2N
Shut Down March 07
84.000
New line SRAR MS 8''
Sept. 07 - Jan. 08
146.106
Rearragement of nerworks for tank P-8759B
April 08 - July 08
114.000
Firefighting Monitor installation in Units U-4900, U-2000, U-3300, U-2600/2500, U-9200 
May 09 - Oct 09 
360.000
Replacement Of Preheaters M-2030 and M-2031 In Unit U-2000 
Shut Down Sept. 09
186.000
Maintenance Works Of Air Coolers In U-2000, U-2100, U-2600,
U-3100, U-3200,U-3300, U-3500, U-3800, U-3900, U-4000, U-4600, U-5400
Shut Down Sept. 09
158.000
Maintenance works of Heat Exchangers M-3401 A/C/B 
Shut Down Sept. 09
60.475
Demolition and Erection Works for Tie-Ins In Old Thermal Building Area.
Shut Down Sept. 09
161.000
Sundry Pipeworks in Units U-2100/U-5400 & U-3500
Oct. 2009
50.830
Mechanical works for tanks In Aspropyrgos and Megara
March 11- in Progr.
600.000